Featured Telecommunications Projects:
 
Station Modifications
MBTA Contract: J70CN01
General Contractor: City Lights Electrical Co., Inc.
Completion Date: January 2001
City Lights Electrical was the General Contractor on this project. The scope of work included: Site work, sign structure fabrication, variable message sign installation, fiber optic cabling, Fiber terminations, certified testing of fiber optic cabling, concrete work, and the installation of CES Bungalows.
 
Bechtel Parsons Video Surveillance
Completion Date: 1995
Installation of video surveillance cameras and cabling along the CA/T to monitor worksites.
 
Blue Line Track, Signal & Power Relocation
MBTA Contract: T12CN01
General Contractor: JF White
Completion Date: 2001
Relocation of fiber optic, telephone and data cabling, wayside telephone equipment, and radiax cabling with yagi antenna under service to allow for construction of the new Blue Line Airport Passenger Station.
 
CA/T - C22A2 ITS
CA/T Contract: C22A2
General Contractor: Allied Signal/Honeywell
Completion Date: On-going
Construction of a state of the art Intelligent Transportation Management System including the installation of: Loop Detectors, CCTV, Variable Message Signs, Lane Control Signals, Fiber Optic Backbone Cabling including Fusion Splicing and Terminations.
 
CA/T - C17A1 Emergency Fiber Rerouting and Repair
CA/T Contract: C17A1
General Contractor: Modern Continental
Completion Date: On-going
Installation and Emergency Maintenance of fiber optic cabling, terminations, and fusion splicing.
 
CA/T Radio Tunnel Antenna System
General Contractor: R. Zoppo
Completed: 2000
Emergency Maintenance of tunnel antenna system.
 
Curry College - Kennedy Building
General Contractor: Suffolk Special Projects
Completed: 2000
Installation of a Star Topology Network including: Category 3, Category 5, Coaxial and Fiber Optic Cabling to allow for full interactive communication across the campus between classrooms, offices, and computer labs.
 
Norwood Police and Fire/Norwood Power and Light
Termination and fusion splicing of fiber optic cable.
 
Omni Parker House
General Contractor: Structure Tone
Category 5 and Coaxial Cable installation.
 
Planet Interactive
Category 5 cable installation.
 
Strawberry Hill Condominiums
General Contractor: JK Scanlon
Completed: 2000
Voice, Data, CCTV, CATV cable installation.
 
Summit
Category 5 and Coaxial Cabling, Network and/or Voice/Data installations.
 
Verizon
General Contractor: Mosler Inc.
Completion Date: 1999
Security installation of Mosler System at 5 locations in the Metro Boston area for Y2K.
 
Woburn Regional Transportation Center
MPA Contract: 1.727
General Contractor: The Middlesex Corporation
Completion Date: On-going
Construction of a new MBTA Commuter Rail facility consisting of Station Building, Platform & Parking Areas. Installed systems include: Public Address, Passenger Assistance Intercoms, CCTV, Fire Alarm and LED Message Signs.
 
Zefer
General Contractor:
Completion Date:
Category 5 and Coaxial Cabling, Network and/or Voice/Data installations.
 
 

"City Lights was selected to do all the power requirements for the whole baggage screening project at Logan International Airport, mandated by the FAA at all the airports across the nation by a January 1, 2003 deadline. It should have taken over a year under normal construction terms. We completed it in just over 122 days."

- Joe Callanan, Executive Vice President

 
Home | Services | Experience | Safety | News | About Us | Contact | Privacy Policy | Site Map